AMECC EXECUTES INSTALLATION OF POWER PLANT - HOA PHAT STEEL COMPLEX STAGE 2.

Hoa Phat Dung Quat Cast Iron and Steel Production Complex has a total investment of 52,000 billion VND, designed with a capacity of 4 million tons a year, the main products are construction steel, high quality rolled steel.

The project is divided into two stages. Stage 1 was implemented in 24 months from February 2017, with a capacity of 2 million tons / year of long steel including 1 million tons of construction steel and 1 million tons of high quality long steel.

The second stage of the project to produce 2 million tons per year of hot rolled steel for mechanical manufacturing, has been implemented since August 2017.

In stage 1, Amecc has participated in installing FGD (desulphurization) systems, cooling tower systems, cooling pipes, main steam pipes, water supply pipes, supply pumps, air separators, I&E systems...

For the second stage, AMECC has just signed a contract with Wuhan Urban Environment Engineering Co., Ltd. on the construction and installation of steel structures and other systems of the Power Plant of Hoa Phat Dung Quat iron and steel Production Complex.

AMECC is mobilizing manpower resources, construction equipment for execution of the works, ensuring progress, quality, meeting the technical requirements of the Investor.

Hai Phong, November 8, 2019