UPDATED INFORMATION OF LONG SON PROJECT
At the end of 2008, Long Son Refinery and Petrochemical Complex was approved by 1/500 People's Committee of Ba Ria - Vung Tau Province in Long Son Economic Zone.
This is the first petrochemical complex in Vietnam with a capacity up to 1.6 million tons / year, capable of replacing imported polyolefins products. The project also includes other infrastructure beside petrochemical production complex, deep-water port.
With the affirmed brand name in the domestic market and regional countries, Amecc is always the first choice of large and reputable enterprises in the high-tech mechanical engineering industry.
In order to affirm its role, Amecc Construction Mechanical Joint Stock Company is honored to receive the Long Son G. Petrochemical SMP Complex Package by the efforts of all Amecc employees and employees will create a guarantee project quality, progress, effectiveness as committed.
Name of project : SMP Petrochemical Complex Long Son G
Project Location : Long Son Island, Ba Ria - Vung Tau, Việt Nam
Contractor : Hyundai Engineering Co., Ltd
Subcontractor : AMECC Mechanical Construction Joint Stock Company
Contract Signing Date : January 10, 2020
Project Duration : 20 months
Scope of work : Structural steel, Mechanical and Piping
Capacity: - Composite steel structure = 1,900 Ton
- Mechanical Installation = 2,100 Ton
- Pipe Installation = 45,000 D/I
- Tank Installation Detail: Diameter = 54m and Height = 21m
Project Images:
Tin nổi bật
-
HỘI NGHỊ QUÁN TRIỆT, TRIỂN KHAI CHỈ THỊ, THÔNG...
Ngày 31/08/2024
-
Lễ Hạ Thủy Tổ Hợp Module Batch #2 Thuộc Dự Án Ras Laffan...
Ngày 31/08/2024
-
Công ty cổ phần cơ khí xây dựng Amecc tham gia chương...
Ngày 22/06/2024