On 12.31.2015 Lisemco 2 JSC signed a contract with Seogwoo Vietnam Company Limited for steel structures of Heesung Electronics-Vietnam. In this project, Lisemco 2 undertake the entire design, fabrication and installation of 1,700 tons of steel structures of the buildings. With more than 2 months progress, coincided at the time of the Lunar New Year holiday of the country, though, after signing the...

 

LISEMCO 2 EXPECTS COMPLETE THE WORK

AT  HEESUNG ELECTRONICS VIETNAM EARLIER THAN SCHEDULED

 

On 12.31.2015 Lisemco 2 JSC signed a contract with Seogwoo Vietnam Company Limited for steel structures of Heesung Electronics-Vietnam. In this project, Lisemco 2 undertake the entire design, fabrication and installation of 1,700 tons of steel structures of the buildings.

With more than 2 months progress, coincided at the time of the Lunar New Year holiday of the country, though, after signing the contract Lisemco 2 has focused all resources of manpower and machines, supplies and materials, embarked immediately on progress. Design work is done in 20 days, an unprecedented short time. The drawing is designed to work accurately, so that  the fabrication work is very favorable. Although the weather was drizzly days on the Tet occasion but the painting & packing work still be completed by the painting team as scheduled.

 

When processing and manufacturing activities are relatively completed, The LISEMCO 2-3 enterprise immediately started bolting work for the foundation. The project requires urgent progress but with several years of experience in construction at site, the Lisemco 2-3 enterprise has mobilized manpower for working 3 shifts constantly, therefore after only 4 days the enterprise was ready to hand-over the ground for installation.

On the date of 02.09.2016 ( is the 2nd day of Tet holidays) in spring boisterous atmosphere, the families gathered together to enjoy the flavors of traditional New Year, while the employees of Lisemco 2 has commenced installation at Heesung Electronics-Vietnam project with a strong atmosphere upbeat. Witnessed the whole process of preparation along with confidence in the technical level of Lisemco 2’s workers, Mr. Chang Soon Jae - General Director of Seogwoo-Vietnam Ltd. seemed satisfied when first column line was erected on the location safely and accurately.

 

So far, after 10 days carried out installations, nearly 50% of the work volume has been done by Lisemco 2-3 accurately and safely. A factory appearance has gradually appeared before the satisfaction of both the Employer: Heesung Electronics-Vietnam, and main contractor: Seogwoo Vietnam Co., Ltd.  Thisstrengthens the relationship between Seogwoo Vietnam  and Lisemco 2, to enhance the long-term commitment, shared prosperity, growth and development between the two companies particularly and Vietnam – Korea generally.

Hai Phong, on 19.Feb.2016