AMECC – AMECC UPDATE PROJECT PROGRESS 17545 BV BATANGAS HRSG 3 UNITS.

Project 17545 BV BATANGAS HRSG 3 UNITS officially started on December 23, 2021.

Project 17545 BV BATANGAS HRSG 3 UNITS is processed and manufactured by VOGT Power International - USA by order of AMECC. The equipment that is processed and manufactured will be transported and installed in Batangas - Philippines.

Total project volume: 3,600 tons divided into 3 Units; Each Unit weighs 1200 tons. The form of outsourcing products is HRSG including: Casing, Inlet Duct, Outlet Duct, Stack, Stair & Platform.

Products of this project are characterized by large size and volume. There are details 32m long, 4m wide, weighing about 60 tons.

By May 3, 2022, AMECC has processed 56% of the contract volume, including:

- Unit 1: About 1,200 tons delivered on May 26, 2022.

- Unit 2: About 1,200 tons delivered on June 4, 2022.

- The remaining volume of Unit 3 will be delivered in August 2022