AMECC - DELIVER SHIPMENT NO 2 OF BLACK POINT COMBINED CYCLE POWER PLANT
In the new spring atmosphere in early 2022. On February 15th, 2022, AMECC completed 2 of 3 shipments of BlackPoint Combined Cycle Power Plant project with volume of 600 tons including casing panels and air ducts.
The Black Point Combined Cycle Power Plant project was signed with customer BHI with a total project volume of 2127 tons of Heat Recovery Steam Generators (HRSG) exported to Hong Kong for EPC contractor is Siemens company.
The biggest package of this shipment is 31 tons with dimensions is 24.7m length, 4.35m wide, 3.1m height. All equipment is exported through Hoang Dieu Port in HaiPhong City.
Final shipment will be delivered here on March 10th, 2022.